Re: Need of setting in different areas and their importance?
Dear Ameya, In production scheduling profile, Plant parameters and MRP group parameters.Some common fields or parameters or plant which can be set or assign to these above area. I need to know why...
View ArticleRe: Make to stock.planning. mrp should not consider sales orders for planning
Vijesh,We have make to stock and make to order process and we are following strategy 40 for both the processYou may have Strategy 40 in your material masters, but you are not actually running strategy...
View ArticleRe: auto-selection of values in configuration screen in sale order? i
Hello, You can explore variant configuration, it is possible to invoke a function module from an object dependency. Best Regards,Ameya B.
View ArticleSAP PP
Hi,Can anyone explain me what is the difference between, planning strategies 10,11,20 and 40 with appropriate examples?E-mail : kotasraj3443@gmail.com Thanks & Regards,Raj Kiran
View ArticleRe: G/L Account No
Hello, There are many threads already explaining this, GL account no, is the general ledger account number, Have you seen the below threads ? what is GL Account and how it is used G/L account no in...
View ArticleRe: SAP PP
Hello Raj, To explain in short, 10, 11 and 40 are MTS strategies, while 20 is a MTO strategy. There is enough material available for this already. Have you searched SCN enough before posting this ?...
View ArticleRe: mrp dates
Hi Amal As I already mentioned, you will find a lot of information about the PIR split on SCN and SAP Help. I suggest you to do your homework and do some research by yourself before asking questions...
View ArticleRe: mrp dates
Moreover, I was checking your old threads and most of them were answered, however, they are still open. When you get a solution for your issue, you should close your threads. If you keep your threads...
View ArticleRe: mrp dates
Dear Caetano ;I am sorry for bothering you but if you go up you will find that I am asking my question well using an example also ! and I also spend time in search that I found a solution with "...
View ArticleRe: mrp dates
Hi Amal I'm not the one who can decide which thread should be closed. I can only see that you have already opened 32 threads and that most of them have at least one answer (most of them more than one)....
View ArticleRe: Capacity split & operation scheduling
Hi Matteo The operation start and finish date is defined by the operation duration and this is calculated according to the scheduling formula from the work center. The standard formula SAP002, for...
View ArticleRe: Batch Split Incorrectly?
Hi Brahmankar, I have attached the screenshot of the scheduling profile. The Always Batch Split check box is not checked.Actually, when there is a batch in inventory that can fulfill the component...
View ArticleRe: MDVP issue - availability check
Hello: How can I know, which Rule is using MDVP when is running? Thanks.
View ArticleRe: MDVP - Collective Availability Check
Hello: How can I know, which Rule is using MDVP when is running? Thanks.
View ArticleHighest priority of Backflush Indicator
Dear SAP Gurus, 1. If I activate backflush indicator in Material master, Workcenter, Routing and Production order. Then which backflush indicator the system will choose for automatic backfushing and...
View ArticleRe: MRP Planned Order Splitting and Conversion
Thank you, so much for your reply.BUT...as I mentioned, splitting PIR's would be splitting them evenly...not line capacity-wiseAlso as far as the quota is concerned, that won't solve my problem either...
View ArticleRe: Automatic Moving of Expired item to scrap storage location ( 23916 )
Hi Kaushal, As per my knowledge standard SAP will not transfer the stock automatically. hence please coordinate with your ABAPer for developing a small report which will execute in the daily morning...
View ArticleRe: Highest priority of Backflush Indicator
Hi Sudipta, As per standard SAP we can maintain the back flush in 4 places i.e. 1. material master : always back flush whenever you try to do the goods movement against this material system will always...
View ArticleRe: Make to stock.planning. mrp should not consider sales orders for planning
Hi Venkatesh There are many existing sales orders with requirement type KSV,,is there any program to change it mass from KSV to KSL? Thanks,Vijesh
View ArticleRe: MDVP - Collective Availability Check
Hello, In MRP 3 view under the header availability check you have the checking group. Checking group is linked to a checking rule via scope of check (OPPJ -> Determine Check) Checking rule for...
View Article