Re: Single PR from MRP run
Hi, Yes you can generate single PR for multiple FERT BOM. For your raw material, in MRP4 view, select Individual/Collective requirement field as 'Collective requirment' that is '2' as shown in screen...
View ArticleRe: Dependent Requirements for MRP type V1/VB
Hi, How can system create procurement proposal for dependent requirements for MRP type V1/VB if stock level of such material will be far above the reorder point and even this stock is used to produce...
View ArticleRe: Start Date in Past: Business Reason
Hello, As far as I know, some customers do not use any scheduling dates proposed by SAP and have scheduling done in external systems integrated with SAP. In such cases, to avoid any scheduling...
View ArticleRe: Dependent Requirements for MRP type V1/VB
Hello Isuru, Dependent requirements are not taken into account when using MRP types VB and V1. In this case, the system checks only the reorder point. It is only used as reference for planned...
View ArticleRe: Start Date in Past: Business Reason
Hello Rahul, In general the system performs forward scheduling when basic start date falls in the past. So in some cases customers do not want this behavior and allow some days in the past. I think...
View ArticleRe: Forecasting Issue
Hi, I think the availability check finds the available quantity as well as the requirements . Please have a look over that . Regards
View ArticleRe: Single PR from MRP run
Please observe that, even if you are using collective requirements, there is no guarantee that system will generate a single purchase requisition. It will depend on the lot sizing procedure defined for...
View ArticleRe: Dependent Requirements for MRP type V1/VB
Hello You can use BADI "MD_CHANGE_MRP_DATA and Method CONSIDER_RESB to display the dependent requirements on the MRP transactions (such as MD04) when using reorder point MRP. However, these dependent...
View ArticleRe: Start Date in Past: Business Reason
Hi Rahul This setting is generally used to avoid rescheduling exception messages. There is also a specific scenario, where there are several requirements in the past for which MRP generates several...
View ArticleRe: Start Date in Past: Business Reason
Rahul,To add to the other expert's excellent answers, let me also share a business philosophy for allowing start dates in the past. It allows a planner to zero in on his worst planning problems...
View ArticleRe: Single PR from MRP run
Thanks Amey Naresh and caetano to take interest in my query. I know little about individual/collective indicator, please correct me if I am wrong but, as per my understanding this indicator is used...
View ArticleRe: Single PR from MRP run
Hi Akshay, You have two FG Y & Z and have common RM X, After MRP Run each Independent Requirement generate Schedule lines and results to two PR for X. You can not Plus it. RegardsNitin
View ArticleWrong alternative BOM selection by FM "CS_BOM_EXPL_MAT_V2 "
Hi All, Header Material has only single alternative valid BOM "0K" . I am executing Function module "CS_BOM_EXPL_MAT_V2" with following selection with alternative BOM 0E. It should display zero...
View ArticleRe: Wrong alternative BOM selection by FM "CS_BOM_EXPL_MAT_V2 "
Hello, Do you mean that the alternative 0E does not exist ? If yes, then the function module CS_BOM_EXPL_MAT_V2 picks up the only alternative which is valid, if you make that single alternative in...
View ArticleRe: Single PR from MRP run
Hi Akshay, As explained above, Yes after MRP run you will get single PR for your above scenario also. Take a common raw material and in MRP4 view, Individual/Coll. field keep '2' setting. Test your...
View ArticleNeed of setting in different areas and their importance?
Dear SAP Gurus, We can set backflush in different areas. My requirement is, Please provide me some basic settings which can be set in different areas like backflush and their importance(means reason...
View ArticleG/L Account No
Hello Guru'swhen creating a purchase PR manually, system prompts to enter G/L account no.Please let me know the role of this G/L Account no? Thanks in Advance,T.Sundaramanickam
View Articleauto-selection of values in configuration screen in sale order? i
Dear Experts, I am running into a requirement where, user will only provide length & diameter of cable as input. I shall use these two parameters in abap Code which shall trigger in VA01 after...
View ArticleMake to stock.planning. mrp should not consider sales orders for planning
Dears We have make to stock and make to order process and we are following strategy 40 for both the process For MTS items we have maintained safety stock So we are considering planned order as stock...
View Article