Re: MRP issue for Spares Material with Reorder point and FX lot size
Hi Caetano, can you Pl tell me steps to perform MDAB. so that all the Net change indicators are marked for that material. BRSachin
View ArticleRe: MRP issue for Spares Material with Reorder point and FX lot size
Hi Rohit, thanks for your reply. I have checked the MD21 Planning file entry and currently no indicator are set. MRP program is RMMRP000 Variant details arePlant-Processing Key - NEUPL for weekly job...
View ArticleRe: MRP issue for Spares Material with Reorder point and FX lot size
Hello MDAB does not mark the NETCH indicator if the planning file entry already exists. This transaction was developed specifically to create the planning file entry when it is missing, not to check...
View ArticleRe: MRP issue for Spares Material with Reorder point and FX lot size
Hello Did you check on transaction MD05 if any exception happened for this material? In addition, are you using parallel processing or are you running on a retail system? BRCaetano
View ArticleRe: Make to stock.planning. mrp should not consider sales orders for planning
Hello Vijesh I don't think that such program exists. Nevertheless, you can double check opening a new thread on the SD space. BRCaetano
View ArticleRe: Make to stock.planning. mrp should not consider sales orders for planning
Hello, You can change the requirement type in mass by using transaction MASSSelect Object Type BUS2032Then select Sales Order Item Data MASSVBAP select field MASSVBAP-BEDAEenter your sales document...
View ArticlePlanned delivery time is not taken into consideration when creating PR
Good afternoon. I am running an MTS scenario, where i am using EX as lot size and PD as MRP type. When i run MRP for my material,MRP creates one Purchase requisition per day (grouping daily reqs, as it...
View ArticleRe: Reducing Forecast Requirements
Many many thanks and please accept my apologies for the late reply!
View ArticleRe: Planned delivery time is not taken into consideration when creating PR
Nikos,What is the planned delivery time you had maintained and hope you had run MRP with planning mode 3 again after changes in info recordDid you notice any exception message for reschedule in or...
View ArticleRe: DOUBT MATERIAL CONSUMPTION OF ALTERNATE BOM
I got answer. I used followup material in two ways. one is with date and another one without date for discontinued material
View ArticleRe: Planned delivery time is not taken into consideration when creating PR
Hi Nikos If the flag is unchecked on OPPQ for the plant, then the planned delivery time should be read from the material master. Make sure that the existing requisitions were deleted and try to run MRP...
View Articlecurrent date scheduling is picking a future date in production order
Hi, When I choose current date scheduling type during production order creation, after scheduling it is adjusted to a future date i.e. If basic start date: 09/09/2015then after scheduling it is...
View ArticleRe: Production order creation Issue
Hi,Planned order to production order is dependent on the master data maintained for a material.Now,there can be various cases for that too.Please elaborate on your requirement.
View ArticleRe: current date scheduling is picking a future date in production order
Hello I suggest you to read carefully note Note. The symptom described on this note is the following:With forward scheduling, the first operation does not start at the order start date. If it has been...
View ArticleRe: Firming Indicator (*) for Scheduling Agreements not consistent between...
Thanks R! Note 103732 provided exactly the explanation that I needed.
View ArticleRe: Availabilty check for the production order
Dogboy, The details on my scenario on the original msg is clear and specify which screen shot you want to read again pls let me know. Or specify the area for which you require understanding.Let me know...
View ArticleHow can I manage batck key in process order component?
Hi, when I create a process order I have a material code that has no value in Batch Key field. So when I release for automatic batch determination, the system doesn't check the batch for that...
View ArticleRe: display 0% load work center in MC38
Kamal,I am not sure about what CM38 why don't you check CM01/CM05/CM07 for work center capacity evaluations. BRKK
View ArticleRe: Capacity split & operation scheduling
You can use two different work centers and create a parallel sequence of your routing. That way, operations on both work centers can run in parallel and the time form the longer operation will be...
View ArticleRe: display 0% load work center in MC38
Hello Do you have planned orders on this work center or only production orders? As mentioned on note 426522, CM28 does not considered production orders by default.You should add the user parameter CY-...
View Article