Thank you, so much for your reply.
BUT...
as I mentioned, splitting PIR's would be splitting them evenly...not line capacity-wise
Also as far as the quota is concerned, that won't solve my problem either
I have decided to use the PIR splitting to maybe simplify my requirement, which is now:
break the 1 monthly PIR into 4 weekly PIRs
Now, in capacity leveling (MF50) I want to split the week 1 PIR into the 5 working days, over 9 machines/lines, according to per day/per machine capacity. Possible?
Week 1 target: 1000 kg
1 machine per day capacity: 100 kg
machine 1 planned fully for 5 days: 500kg
then since machine 1 is full, it should automatically go to machine 2 (production version sequence 2) and plan that until that is full and so on.