Re: List of Planned Production Operations
Dear Edison, Only production orders has the operation over view details planned orders doesn't have operation overview details hence system is taking list as headers by default if you selected both...
View ArticleRe: List of Planned Production Operations
Yes Correct, Sorry I did not check your question completely, with standard COOIS report, we can have operation details for Production order only. we can go for development as mentioned by experts....
View Articlecomponent allocation changed date and time
Dear friends, I have one requirement.I have one production order with valid routing.we assigned some components for the operation.This production was completed. Again the user changed the component...
View ArticleRe: Serial Number Duplicacy for same material during MFBF
Dear R Brahmankar, Thanks for your valuable reply Closing the same Best Regards,Madhukar Poul
View Articlequota arrangement - reduced allocated quantity when creating production order
I have searched the forum and the web for this issue about the quota arrangement but the answers I found did not apply to this case.I also found 2 old notes: 710639 and 730070 which are implemented in...
View ArticleHow to delete last serial number using IQ02
Dear All, Scenario: Through Interface we push mass serial numbers from non SAP to SAP with pairing data Condition: No same serial number push from non SAP to SAP System Suppose X is material having...
View ArticleRe: Where is Data that automatically populates a PI-Sheet stored?
Would you like to try and make it two for two!?!? I am struggling to find a way to extract data from our Repeated Data Request Tables that are built into the PI Sheet. Do you have any tips for this?...
View ArticleRe: How do I extract Data from a table inside of a PI-Sheet
Hi WilliamPlease try this setting in O10C , I think you are facing problem to extract BOM componentsAssign '01' to the consumption instruction category which you have maintained.And also check your...
View ArticleRe: Filtering MD16 for PlORel and PlOrd.
Hello In my system, everything is working fine. All the planned orders are selected when using the selection based on the MRP controller. Maybe you can debug on MM61PF22 -...
View ArticleHow this mrp run takes place,sometime customer requirement getting...
During mrp run Customer requiement are considering some time and system does not consider the customer requirement..how it is behaving erratic ?
View ArticleSTLBEZ field in production order
Dear experts, I have fews order in which STLBEZ field is appearing as blank.In most of the orders it got filled by the header material only.But now i want to update this field(STLBEZ). how can i do...
View ArticleRe: How this mrp run takes place,sometime customer requirement getting...
Hi, can you share the screenshot to understand the issue. Thanks &Regards Sandeep Kumar Praharaj
View ArticleRe: How this mrp run takes place,sometime customer requirement getting...
Ajit,Within Sales/Distribution 'Basic Functions' configuration, you define which types of sales requirements should be passed to MRP. It is common to have certain sales objects to be excluded from MRP...
View ArticleCorrected to Total Consumption in MVER
We recently launched a new facility that has no consumption history. However all of the product in that new facility was previously used at another plant. For forecasting purposes it is desired to...
View ArticleRe: Corrected to Total Consumption in MVER
Hello You can use function module MB_UPDATE_MATERIAL_CONSUMPTION to update the consumption. Check this WIKI with an example program: Consumption Value UploadConsumption Value Upload - Code Gallery -...
View ArticleRe: STLBEZ field in production order
Hello See this document for details: http://scn.sap.com/community/erp/manufacturing-pp/blog/2014/02/25/revision-level-for-pp-masters BRCaetano
View ArticleRe: Production Order numbers are not generated in sequence
Swapna,I have an understanding that when certain processes run, a block of numbers (order number, system assigned material numbers) can be reserved for use. If a block of 20 is reserved and only 15 are...
View ArticleRe: Production Order numbers are not generated in sequence
It should not be possible to impact in that manner.
View ArticleChange component allocation in CEWB for multiple routes
Hi All I experience a huge problem. I will describe the problem in a very simple manner: Material A consist of: 0010 Material C 0020 Material DMaterial B 0010 Material C 0020 Material...
View Article