Hi All
I experience a huge problem.
I will describe the problem in a very simple manner:
Material A consist of:
0010 Material C
0020 Material D
Material B
0010 Material C
0020 Material E
We have two routings:
1. Routing for material A
2. Routing for material B
Now we want to change component allocation of Materal C from operation 0010 to 0020.
In standard SAP i will use CA02:
1. for Material A and change assignment of C
2. for Material B and change assignment of C
I would like to change the component assignment of material C for both routings in a Mass Change
I have read about CEWB, but i can not find a way to solve this.
Do you have any experience/solution to this problem