Re: Process order TECO and CNF
Hello If the issue is solved, please close the thread. BRCaetano
View ArticleRe: Monthly planning and MRP run
Hello YOu can use the same BAdI to make POs and schedule lines not relevant to MRP. BRCaetano
View ArticleNew bee to SAP PP World
Hi All, I just recently joined SCN, and looking for SAP PP training... please suggest me how to start on this, if there is any soft copies please share me @ skred16@gmail.com.... Thanks in Advance...
View ArticleComponent Allocation for Alternative Sequence
Dears, I have the following case: there is one routing with different alternative sequences, I am trying to allocate some components of the BOM to the alternative sequence but while creating the order...
View ArticleSOP Rough cut capacity planning explosion routing of the child produt group.
Dear Gurusi would like to know if in the SOP capacity planning analysis is possibile to explode the routing multilvel in order to have the total requirement for the child of the product group.I would...
View ArticleRe: Generate a single Purchase requisition
Hello, As was mentioned by Caetano, the MRP only generates requisitions with 1 item/material.You could assign multiple requisitions into 1 single purchase order. Kind Regards,Mariano
View ArticleRe: Components appearing twice in process order
Hi, Does it occur for 1 process order or it is happening for all your process orders?If this occurs only for 1 process order..Kind Regards, Mariano
View ArticleProduction Order
Hi Gurus , In one of the scenario user wants to determine the printer based on plant &production order type combination .As I know we have three options available (1. Printer from user master...
View Articleresb supply area from production order
Hi allI need to understand from where is taken the supply area in resb form production order.My problem is that I have a production order from which in resb some components have supply area and othners...
View ArticleRe: resb supply area from production order
Hi Shila, Did you check the workcenter basic data tab ? Supply areas are maintained in workcenter master data and BOM item details of components (for material staging). Regards,Rohit
View ArticleRe: resb supply area from production order
Hi Shila, Please read this documentation that explains how it works https://help.sap.com/saphelp_470/helpdata/es/c6/f8413c4afa11d182b90000e829fbfe/content.htmKind Regards, Mariano
View ArticleRe: Production Order
Hello, Your conclusion was correct.You can do it using OPK8. Put * in the MRP controller. I suppose that if you re print the orders previously created, the new printer assign in OPK8 should be...
View ArticleAutomatic Sequential Line Item Numbering for Row's in a PI Sheet Data Table
Good afternoon, I am attempting to build a PI Sheet which uses a Repeated Data Request table. A member of our validation team has asked if it were possible to have each row auto populate with a line...
View ArticleProduct Hierarchy Reports
Hi Dear Gurus, Nowadays I've implemented Flexible Planning with my own Info Strucrure, but I need your help in order to get a Planning Hierarchy Report that could display all upload levels , i.e Plant...
View ArticleProcess Order Pick List Prinitng from Resources
HI, We are unable to print pick list from resource setting. Here is my configuration: What are the other setting to be done to print pick list from resource printer. Please suggest. Regards,Harry
View ArticleRe: CS_BOM_EXPL_MAT_V2 : need more(10) decimal places for the BOM quantities
Hi,you should handle the header bom quantity in order to have this conversion quantity. In this case all component should be calculated according to header quantity Daniele
View ArticleRe: Capacity planning
Hello This triangle appears when the order has been partially completed and it identifies the confirmation date. BRCaetano
View ArticleRe: Automatic creation of Planned Order
Hello As already mentioned here, using MRP to create the planned orders is the best option. The problem here is that, both the planned order dependent requirements and the production order reservations...
View ArticleRe: Capacity planning
Hello Are you using REM? Did you already posted a backflush for the planned order? BRCaetano
View Article