Re: Rough cut capacity planning

Dear Prasad, The available capacity will be calculated based on the Work centre which you have assigned in the Rough cut planning profile i.e. In Work centre capacity header tab we will assign the...

View Article


Re: TECO Issue

GIER is a status within a production order.

View Article


Re: Phantom Assembly BOM is not getting exploded in Routing During Component...

Hi Ravi, I have exactly the same issue, I validated all possible related config to avoid phantom not exploded on the routing with no success. The only useful information I found is on the bellow SAP...

View Article

Re: Process Order Confirmation

Hello, In standard SAP there is no functionality sent confirmation of order for approval.You may check the BAdi WORKORDER_CONFIRM method AT_SAVE with custom logic to check what are tolerance define....

View Article

Re: Forecasting with MRP type PD

Hello, Check configuration of MRP type in OMDQ under MRP Ind. Forecast MRP indicator forecast should be not transferred to MRP. Or you can use MRP type like VV.Best Regards,R.Brahmankar

View Article


Re: BOM Explosion - ECN display - Assembly part number Explosion

Hi , Thread Closed. Vignesh.V

View Article

Image may be NSFW.
Clik here to view.

CS11/12/13 to show component with Vendor info

Dear Gurus, One of my searches was such that how can Vendor details of components shall be shown in CS11/12/13. Also in other side if in case if same components is being supplied by multiple vendors in...

View Article

Re: Forecasting with MRP type PD

Hi RupeshThanks for your reply.I make same changes & it is working.In case of MRP type VV, sales order are not displaying in MD04.Can you suggest what is the reason? RegardsAshish

View Article


Re: Production orders with stock-relevant semi-finished products

Thanks Kumar for your feedback.We do not prefer 2 production orders because we do not want to plan the 2nd operation separately: only the 1st operations should be planned. The 2nd operation can start...

View Article


Re: BAPI_PRODORDCONF_CREATE_TT Slowness

Hello One option is to define that the goods movements will be posted later in a background job. You can create this process control key on transaction OPKC and then refer it on your order type...

View Article

Re: Error in flexible planning (MC94), Need SAP tables for planning hierarchy...

Hi Caetano/Rupesh,Thank you.Program RMCP6FLS or t code MC9A help me to create planning hierarchy automatically. Can I add new characteristics value in planning hierarchy MC62? Will it cause any issue...

View Article

Re: Production Order with output based on quality

Sorry that I wasn't clear. We have a manufacturing process where discrete items are made on a Production Order. At the end we test each item to determine quality and based on the results the item can...

View Article

Re: User exit for MRP planning - change planning logic

Mahesh, Very late answer but... You may think the solution differently by implementing a solution that tackle inventory balancing between plant. see Inventory Balancing Cheers, Daniel

View Article


Image may be NSFW.
Clik here to view.

Re: Monthly planning and MRP run

Dear Caetano Almeida Thanks for valuable help for suggesting BAdi. Now I have implemented a BAdi in the MD02 to drop all MRP relevant open documents from previous months it is giving a results but I...

View Article

Re: interface between SAP and MES

Hi Ani,  Go through following document.This will help you out. Cost Optimization with Real Time Stock Status Update from SAP to MES  RegardsPrasad

View Article


Re: CS11/12/13 to show component with Vendor info

Dear Caetano, Thanks for reply. In S note it shows navigation path to get the vendor name,actually I was not able to find any tab named as Purchase order on double clicking the item....but cant the...

View Article

Re: Process order TECO and CNF

Thank You, Created a user status to restrict it Regards,Aziz

View Article


Re: SAP MES integration

Dear srini, I have the one requirement as below. Please help me on this if you have any document or solution how to prepare the document. Please provide the process details of intial stock posting from...

View Article

Image may be NSFW.
Clik here to view.

Components appearing twice in process order

Hi, I have a peculiar issue. While creating process order of a material, all components are appearing twice, whereas in BOM they are single line item. I have found out that there are 2 ECR numbers. Is...

View Article

Re: SAP MES integration

GS, no problem, the integration betwween your system and MES is ok ? this is the only issue. But I understand that the best way is just let MES control the Production Order. The other activities mus be...