Re: MD62 Screen PIRs in RED
1. Red color normally indicates warnings. Maybe you will get an message "Date in planning time fence" or similar when saving. Check also trx OMP9 to adjust message to your requirements. 2. Trx MD62...
View ArticleRe: WM-PP interface - costs missing --> staging not done
Finally, we found out that the reason for the failing staging was not related to costing. It seems that the work scheduling profile in the material is used - even if the order type contractis this....
View ArticleRe: sap bom error: numerical entry is not supported for external item ids
Hi Saravana, Please remove the Item id values(external values) and enable recurs.allowed tick mark, then you can create the BOM . Thanks, Dileep
View ArticleRe: Production Order from Non SAP system how to manage
HI GurU, just want to check as well. For example. We have 3 routing in a production order. In the non sap system we decide to just change this 3 routing we jsut use routing 1 and 3. Then replace...
View ArticleRe: Calculation of Automatic Reorder Point
Hi MRP type: VM, Lot size: EX. Planned Delivery Time: 5, Safety stock is 0 (zero) In Forecasting view put below dataForecast model: D, Historical periods: 1, Forecast period: 1.In consumption value tab...
View ArticleRe: To restrict users on Component Backflush in MFBF
Hi Ramesh, Create a Transaction variant for MFBF and disable the component backflush in it. Regards,Anupam Sharma
View ArticleRe: To restrict users on Component Backflush in MFBF
Dear Anupam In Transaction Variant Radio buttons are coming in non-editable mode and so not able to make any changes. With RegardsRamesh Kumar
View ArticleProcess order confirmation issue
Hello experts, We found a difference betweenthe activity quantity: 9284,826 HL and the quantity to be notified: 33807 PC.If we check material conversion, that´s not the reality: Real...
View ArticleControl Plan Assignment Routing in Reference Operation set
Dear Team, I have created control plan (CP) in transaction QPCP. Now I would like to assign this control plan while creating the reference operation set. How to assign the CP in CA11? If I assign the...
View ArticleRe: Process Order Confirmation through BAPI
hi, Steblyuk, which enhancement you use, You solve this problem or not
View ArticleRe: Calculation of Automatic Reorder Point
Hi, did you assigned any rounding value or service level % or GR processing time ... Thanks With regards,Dinesh V.
View ArticleRe: Calculation of Automatic Reorder Point
HiI didn't assign any rounding value. Service level % & GR processing time are also 0.I have given only PDT 5 days. RegardsAshish
View ArticleRe: Process order confirmation issue
Hi Experts, A gentle reminder.We found a difference betweenthe activity quantity: 9284,826 HL and the quantity to be confirmed: 33807 PC.If we check material conversion, that´s not the case: Real...
View ArticleRe: Goods issue after MRP Run
Thanks alan Kang. This issue closed.thanks for everyone. By Selva
View ArticleCopy Alternative of BOM
Hello All, I have copied BOM from one plant to another using LSMW, but only first alternative is copied. Now I want to copy remaining alternatives to respective BOMs. Please suggest the process for the...
View ArticleRe: Mass maintenance of planned price in Material Master
Hi Sangharsh, I'm trying to use transaction code R2RMM126.but upload file format is not working for me.Could you please let me know the file format for this transaction code. Material PLANT...
View ArticleRe: Changing the BOM daily - Food Catering Business
Hi Kumar I think that you should use planning strategy 70 to plan at component level. That way, the BOM changes will not affect the raw material procurement. Otherwise, you can suggest your customer to...
View ArticleRe: MRP duplicates planned orders
What is your support package? Is this issue happening when running MRP on MD01 or MD01N?
View ArticleRe: MRP duplicates planned orders
It seems it happens with MD01.In this moment I'm trying to check OSS note 2181198.
View ArticleRe: MRP duplicates planned orders
Hello The error corrected by this note may lead to the symptom observed on your system, since the requirements are considered twice by MRP during the net requirements calculation.If the note is not yet...
View Article