Hi,
How can system create procurement proposal for dependent requirements for MRP type V1/VB if stock level of such material will be far above the reorder point and even this stock is used to produce assembly then also it will not go below the reorder point. This is standard SAP behavior hence dependent requirement are not getting created.
MRP type V1/VB will be planned during MRP run if the stock fall below the reorder point only. If you want to create the dependent requirement then change the MRP type as PD.
Regards,
Naresh