Re: Start Date in Past: Business Reason

$
0
0

Hi Rahul

 

This setting is generally used to avoid rescheduling exception messages.

 

There is also a specific scenario, where there are several requirements in the past for which MRP generates several purchase requisitions on the same date. If this is not desired, the start in the past flag must be checked. See the note below for details about this scenario:


52448 - MD01: Several order proposals on one day

 