LTP planned order to be created with different order type

Hi All, I need your suggestions to differentiate the simulation planned order and the operative planned order. At this moment the simulation order type is same as the operative order type after running...

View Article


Re: LTP planned order to be created with different order type

Hello It is not possible to create a new planned order type. The planned order type is automatically determined by MRP, depending on the planned order purpose. For example, for example external...

View Article


Re: Scheduling Automation in CM25

Hello I suggest you to take a look on the following document: CRP Basic Settings part 4 - Running Capacity Leveling in Background BRCaetano

View Article

Re: Creating planned orders during MRP run

Hello Thank you for the update. If the issue is solved, please close the thread. BRCaetano

View Article

How Scheduling parameter start date in the past to be set for X days

Hi All,The planner is making the production schedule in ABC planning tool and transfers this to SAP.On a daily basis the planning is reviewed and rescheduled to the actual production. With the...

View Article


Re: IN COR6N t.code Need to change 15 actual activity

Dear Prem, Thanks Lot for reply, its working Fine while enter the one operation, but second operation like 0030 does not take it ,It will  take  default as 0020 operation. I want to change the activity...

View Article

Re: IN COR6N t.code Need to change 15 actual activity

Hi, You need to confirm the operations one by one. Once you confirm 0020, try the remaining operations step by step ThanksPrem

View Article

Re: IN COR6N t.code Need to change 15 actual activity

Dear Prem, Super it working Thanks lot..... If I change the second operation yield qty what is the impact of activity qty &priceEx 1 operation yield qty was 100 . 2 operation yield qty I have...

View Article


Industrial waste material treatment process mapping in PP

Hello....Experts. I want to map industrial waste material treatment process in PP for my client along with CO.Client has a requirement for process based costing. The waste is received from different...

View Article


Re: data table for mmbe

Check tables MARD, MSKA, MSKU, MSPR for unrestricted-use stock. Fields are MARD-LABST               MSKA-KALAB               MSKU-KULAB(Customer Consignment)               MSPR-PRLAB  Regard'sasim

View Article

Issue with GR Qty - Batch Specific UOM

Hi, I am facing problem while posting Goods Receipt for Raw Milk in Liters as the KG equivalent is not getting derived properly. For raw milk stock keeping unit is KG and receiving unit is liters....

View Article

Re: Issue with GR Qty - Batch Specific UOM

Hi Anil, The batch specific UOM is maintained as 100 KG / 103 L = 0.971 KG/L.Instead, the first screenshot shows you have Plan value as 1.03 KG/L. This is incorrect.So, as per the settings, you are...

View Article

Re: Issue with GR Qty - Batch Specific UOM

Hi Prem, The Plan Value refer to Raw Milk Batch Density which the QA team will define as one of the Characteristic value. If i am making a GR for 100 litres (at Density = 1.026 KG/L) it should create a...

View Article


individual capacity update automatic

hai friends,      I have booked 4 individual labor capacity of one work center to particular prod order for next day. The next day one person not came client required automatic update on absence need...

View Article

Re: individual capacity update automatic

Chaitanya,I don't know exactly what your client wishes to automate. I hope he does not expect that SAP has some magical way to detect that an employee is missing, and then automagically reschedule the...

View Article


Re: URGENT:UNABLE TO DO GOODS ISSUE IN MIGO

Hi Phani,  Go to the order to the components tab, check if you have checked the Final Issue indicator for each component. If this is the case, remove the flag and save.  Kind Regards, Mariano

View Article

Re: To copy the component assignment

Hello Brahmankar!   Thanks for your reply.   About the CEWB, I can't to do copy any material because the field is disabled.On the picture last and next, you can see that the field doesn't allow that I...

View Article


Re: Issue with GR Qty - Batch Specific UOM

Hi Prem/Amaranth, This issue is fixed now, I have maintained the required config setting @ Define Calculation of Base Quantity from Proportion Quantity under Batch Management.  Thanks for your...

View Article

Re: Material is blocked for single item planning error message in SM58 for...

Hello Mastan,  You need to check what this user INT_MM01 is doing. It might be trying to edit a sales order at the same time when MRP job is running, which is causing a lock. RegardsAbhishek

View Article

Re: To copy the component assignment

Hello, Please check the work area in OP77 Component assignment tick is active.Also check the by implementing SAP note  1539919. Best Regards,R.Brahmankar

View Article