Re: Configurable Material, MTO and planning strategy

Hello Please observe that the configuration number will be only inherited by components that are still linked to the sales order special stock. In addition, it is not possible to use a MTO special...

View Article


Re: Manual reservation for Production Order ?

Hello Alex: If you want to consider fixed incoming element in the available check , the component's checking group should be "02 Individual requirement" instead of "CH Batches".But It's means you have...

View Article


Re: Manual reservation for Production Order ?

Hello As far as I know, the offset cannot be changed on the planned order, but you can change directly the requirement date for the planned order components. BRCaetano

View Article

Image may be NSFW.
Clik here to view.

Re: how to add an addtional tabpage in F4 help of transction code CO03

Dear Caetano, It helps me a lot, thanks very much!!!

View Article

Re: Stop confirmation in ECC when stock of component in EWM s.loc does not exist

Hi Brahmankar, I checked the note & the issue we are facing is not matching with the symptom mentioned in the note.We are planning to raise an OSS message. But I further changed settings to allow...

View Article


overlapping of orders in cm25

Generally overlapping of orders end date and start date should not happen in cm25 screen. could you advise if so, what should be the different reasons for the same. observed that in cm25 screen when we...

View Article

overlapping of operations

what should be the different reasons for overlapping of operations i mean say operation 10 scheduled end time 10:30 am and observed that operation 20 scheduled start time 10:25 am. how to eliminate...

View Article

Re: overlapping of orders in cm25

Hello If you have more than one individual capacity defined on the work center, you can dispatch more than one orders on the same bucket. BRCaetano

View Article


scheduling of operations

as we aware, we have 3 activities (setup, machine, labor) defined in work center which will be assigned in operation. each activity will have formula for scheduling. when we check start and end date of...

View Article


Re: scheduling of operations

Hello Scheduling and capacity requirements are different things. The capacity requirements are calculated according to the formulas defined on tab capacity of the work center. There is one formula for...

View Article

Re: overlapping of operations

Hello Overlapping is defined on the routing. On the operation details, you can define the option "no overlapping" and the order operations will not be overlapped.  Please observe that, if your work...

View Article

Image may be NSFW.
Clik here to view.

Follow-on functions for production order

Dear experts, In HUM discrete production, I am using TCODE COP1 to plan end product HUs. In the menu bar, I can see that there are two "follow-on functions": "Order confirmation" & "Goods receipt...

View Article

Re: Scheduling a CNF order

We use backwards scheduling,  While working Production orders we need to adjust an operation within a route to a new date. I.E. previous Ops are "CNF", we need to adjust op 0120 to 2/1/16. We dispatch...

View Article


Planned scrap in production orders

Hello all, I am a new user and would much appreciate your support! I am very confused by the way that SAP calculates the committed quantity for a production order. In my BoM I have 3 items which are...

View Article

Re: Automatic creation of Planned Order

Thank you all dear experts for your answers they were very helpful.

View Article


Re: Reverse Production Order

I see. I reckon as long I do reversal for settlement, that should be good enough as far as variance calculation is concerned?

View Article

Re: Not able to close the production order

Hello Bhage, The this is not a standard error message.. hope you people has done some enhancement. as per the error please check the Batch number for component in the component overview and header...

View Article


Re: Reverse Production Order

Hello, When u execute the variance calculation, system just calculates the variance but real posting happens at the settlement level.When you reverse the settlement of the order, variance also gets...

View Article

Re: Weekly forcast

Hello,   In MD62 you have an option to split Weekly forecast.   Go to tab page: Sched. lines, menu: Edit -> Split perd online.In OMPH  here you can define Split your Forecast for MRP. You need to...

View Article

Re: Get the Details of BATCH classification data In MASS

Hello, Did you check MSC5N and BMBC? Best Regards,R.Brahmankar

View Article