We use backwards scheduling, While working Production orders we need to adjust an operation within a route to a new date. I.E. previous Ops are "CNF", we need to adjust op 0120 to 2/1/16. We dispatch the operation in the PPO to the new date by using "operation", "dispatch". The order forward schedules from that date, but if we have a CNF in any operation, scheduling the remaining ops does not carry out as planned.
↧