Re: Material has MRP type ND but still sales order does ATP eventhough there...
Hi Eric Sun, Did you check CO09 for a better understanding of why the confirmation is done?Even if your MRP type is ND, if you have an open replenishment order, this can be the reason of your...
View ArticleRe: CM01 capacity requirement only calculating for 1 planned order not others.
Hello Mariano, Control key is checked & enable with scheduling and detail capacity requirement.capacity formula using standard formulaRecipe also checked, its valid & production version also...
View ArticleRe: CM01 capacity requirement only calculating for 1 planned order not others.
Hello I'm quite sure that the issue is caused by a program error, which is corrected by the already mentioned note. Please implement it on your system and check again.RegardsCaetano
View ArticleOverpick on TO causing problems on PI Sheet
Our system is set up with WM/PP interface with TR for material staging to PSA created at process order release. Batch determination happens at conversion to TO. All of our materials are set up as pick...
View ArticleRe: PI Sheets....!!
Experts still waiting for your valuable inputs and help.I have to give demo of PI sheets to client. Regards,Amit
View Articleno planned order created
Dear Team I have upload some new items that have PIR in plant 1 and will be produced in plant 2 , I maintain the special procurment key as other old material have the same case, now when running the...
View ArticleRe: no planned order created
Hello Check the document What can I check if MRP does not plan a material? BRCaetano
View ArticleRe: PI Sheets....!!
Hello Amit These link can help you:http://websha.de/xstepcafe/ In addition, you can get more information and examples in these handbooks:TSCM42 Planning & Manufacturing II Unit 12: Optional...
View ArticleRe: MRP related issue
Dear Sir, i have entered demand plan of finish goods current month weekly basis and next 3 months monthly. according to below screen my problem is system result as follow for some material. my concern...
View ArticleDisabling Final Issue indicator in component overview
Hi experts, Happy new year in advance... Their is one requirement where in user wants to disable final issue indicator check box in component overview of CO02, so that no one can manually tick the...
View ArticleRe: Planning Type - Planing Start
Hi,Go to MC8B and enter the planning type you are using in the inside of planning type click on the button planning type info button and in the next screen in the Historical periods maintain the number...
View ArticleRe: Disabling Final Issue indicator in component overview
Hi Mukesh,You need to use screen variants for this. Check the below Link Transaction and Screen variants with an Example ThanksKumar
View ArticleRe: SOP Actual Sales - Actual Sales Last Year
Hello Ameya Hope you are using Flexible planning method. Do you want see the past sales figures on flexible planning table at MC93 /MC94 Pls correct me if my understanding is wrong
View Articleshelf life
Dear Friends, This is my requirement as below. My client maintaine the Room temperature based on Batch shelflife.When the material recived user enter the batch time like 300 hr 200 hr depends on...
View ArticleRe: Disabling Final Issue indicator in component overview
hi Mukesh, Do you want this field is to be disabled in CO02, right? so it does not matter whether it is final or partial confirmation,please note for screen variant, the screen will be same for user....
View ArticleRe: CM01 capacity requirement only calculating for 1 planned order not others.
Thanks Caetano Yes, you were absolutely correct, after implementing the suggested note 2192359 and re run the MRP it generated all the planned orders with scheduling.Thanks a lot....!! Best RegardsPiyush
View ArticleRe: shelf life
I have not yet seen such functionality in SAP. You would at least need to declare the cold room as a separate storage location and then do transfer posting to another storage location if you remove...
View ArticleRe: ask : Assembly scrap and expected yield variance
Hello This his is a customizing transaction and you can also find it on SPRO.You must create a profile and assign to the material master. BRCaetano
View ArticleScrap Variances and Lot Size Independent Activities
I am working on explaining, in great detail, how scrap variances work to my superiors. I am struggling on understanding how lot size independent activities are allocated into the scrap variance...
View ArticleRe: order teco but again in md04
CHECK THE PEGGED REQUIREMENT WHY IT IS RAISING FROM MD04 MENU. YOU CAN FIND WHAT IS THE CAUSES TO RAISE THE REQUIREMENT
View Article