Our system is set up with WM/PP interface with TR for material staging to PSA created at process order release. Batch determination happens at conversion to TO. All of our materials are set up as pick parts. Upon confirmation, batches and quantities fulfilled by WM are updated in the process order. These are also updated in the PI sheet so our operators only have to review and confirm instead of entering any quantities or batches when performing GI 261 of components in COR6N.
The problem occurs when WM confirm a greater quantity than what is required. This updates the qty in the process order and the confirmation/GI driven by the PI sheet. Our GI numbers need to be static (original requirement qty, not what was confirmed on the TO) as they are a food recipe. Is there any way to only update the process order to the required amount. I.E. have it ignore the fact that WM "overdelivered" against the requirement?
Hope this is clear. It is my first post. Thanks in advance.
Daniel