Re: CM01 capacity requirement only calculating for 1 planned order not others.

$
0
0

Thanks Caetano

Yes, you were absolutely correct, after implementing the suggested note 2192359 and re run the MRP it generated all the planned orders with scheduling.

Thanks a lot....!!

 

Best Regards

Piyush