Hello
I suggest you to read carefully note Note. The symptom described on this note is the following:
- With forward scheduling, the first operation does not start at the order start date. If it has been defined in the scheduling parameters that the basic dates are to be adjusted the basic date is moved to the future when you perform forward scheduling. Therefore, the basic date can be moved to the a date in the future, when you do today scheduling.
The solution for this issue is to change the routing alignment key. You should select an alignment at earliest date if the order is scheduled forwards (current date scheduling).
You can find the alignment key on the routing (transaction CA02), clicking the button sequence.
Best regards
Caetano Almeida