Re: Production Version link to Customer
Hello It is not possible to link a production version to a customer. In fact, on a MTS scenario, there is no reference to the customer on the planned orders. There is a BAdI which can be used to...
View ArticleRe: Calculation of receipts in Dynamic Safety Stock
Hello You should consider only the receipt elements quantity, not the available quantity. In your case, it's only the planned order quantity. The available quantity is the result of the accumulated...
View ArticleRe: DMS integration with PI sheets
Hello Ameya Thanks for the reply. When you say that I should write my own logic, do you mean use the FM on the characteristic (Z)PPPI_STRING_VARIABLE? I'd appreciate if you can provide more details and...
View ArticleRe: During GR We are getting error "Number range for trans./event type WF in...
Thanks Ameya for the reply. My issue is resolved. I am closng this issue. Best RegardsRam
View ArticleRe: Development of manufacturing process
Hello Krishnendu, Interesting to know why you need this . The only way I believe you can obtain this information is by going through the release notes across various SAP releases available on service...
View ArticleRe: Calculation of receipts in Dynamic Safety Stock
Hi Understood now. Thank you for brief explanation. Best RegardsSandeep
View ArticleRe: Calculation of receipts in Dynamic Safety Stock
Hello Thanks for the explanation. Understood the concept now. Best RegardsSandeep
View ArticleRe: BAPI / FM to Change Control Key In Production Order Operation
Hi Ameya Beri, The same result I got... Actully I created YBAPI_ALM_ORDER_MAINTAIN by reomving some coding, and it works. But I still prefer to BDC. I wonder if someone has better solution. Thanks for...
View ArticleWork Center Order in CM01 ?
Dear Seniors, Please let me know if there is a way to control the order in which the Work Centers appear in CM01.We want to have them in a logical order based our WC sequence Thank you,Alex
View ArticleCM01 - Factory Calendar Day in format of 6873 instead of the date format ?
Dear seniors, We want to display in CM01 the working days based on the factory calendar.When I make the setting in general settings to use the Factory Calendar as a period, I get the Factory Calendar...
View ArticleRe: PI SHEET
Hi Mohan, Actually I am also stuck in the same situation, have u got any solution in that context? Regards,Chetan.
View ArticleATO - ATP Check for BOM Components
Dear Team , I am working with ATO strategy (82 - Assembly orders with production orders) I have FERT material M1 for which I have assigned the planning strategy 82 & Availability check 02-...
View ArticleRe: Change quantity of component while reading BOM in COR1
I haven't found any badi / exit for this. I achieved by creating an implicit enhancement point at the beginning of FM CO_BC_INSERT_CMP_OF_ORDERS.
View ArticleRe: ATO - Strategy 82 - PIR Consumption & Reduction
SK SK,Correct. Same as Caetano's response. Best Regards.Rajen
View ArticleBAPI to Update "Delivery Completed (AFPO-ELIKZ)" flag
Hi All, is there any bapi to update "Delivery Completed" flag under goods receipt tab in Production Order? i have tried "BAPI_PROCORDCONF_CREATE_TT " but the value is not getting updated and i got the...
View ArticleRe: BAPI to Update "Delivery Completed (AFPO-ELIKZ)" flag
Hi Ranjani, Why do you need bapi, you can create LSMW or if you need it in program you create BDC. In production order header in goods receipt tab tick the delivery completed tick mark. regards,Solomon
View ArticleRe: BAPI to Update "Delivery Completed (AFPO-ELIKZ)" flag
Thanks Solomon for your quick reply. Yes i need this as program. if there is no BAPI then i will go with BDC only. can't we use this bapi - "BAPI_PROCORDCONF_CREATE_TT" for this update process?...
View ArticleRe: Release of order not possible: CO118
Hi, Can you assign a dummy batch for the component & try to release the order.if you are still facing error kindly share the screenshot of error. Thanks & Regards Sandeep Kumar Praharaj
View ArticleRe: BAPI to Update "Delivery Completed (AFPO-ELIKZ)" flag
Hi Ranjani, If you need delivery completed status than you have to deliver (GR) the total order qty in the production order. By this confirmation BAPI you cant do it.You need to fully gr the order qty...
View Article