Re: MCPS - LIS update the last changes on the production order as TECO - Time...

HelloOn transaction OPL5 you can define that the "release version" will be stored for an info structure. The release version is the version at the time of the release, it means that the values on the...

View Article


Re: General extra material's requirement when MRP

Hi Solomon,     Thanks for your reply.     Your last words "enter material B in bom of A" ,  could you speak more detail ?   Now our users all hope the bom  A = A + B, then PIR on A,  MRP run then...

View Article


Re: General extra material's requirement when MRP

Hi Hung, Enter Material B in BOM of Material A with the quantity of Material B same as the base quantity. BOM Header : Material A     Base Qty 1 PCBOM Iteam  : Material B    1PC When PIR is being...

View Article

Re: WIP Batch

Hi Uday, After creating the last WIP batch, select the WIP batch and in the WIP GR table; select the GR line item and  click on ‘assign GR batch’ button. This creates a relationship between the Goods...

View Article

Re: Change quantity of component while reading BOM in COR1

Hi Tiru,  I have solved such an issue with an enhancement at the end of the FM GET_STPO.  Here you can change "internal table WA" for change in BOM data. If you want to delete or add a component, you...

View Article


Re: MCPS - LIS update the last changes on the production order as TECO - Time...

Hi  Thanks for the help, I understood about the version actived on the OPL5 to take  a information on the LIS tables or (MCPS), but in cases where I released the order with a quantity of 1 UN and after...

View Article

Re: Assessment stock by material group

Hi! Thanks for your support... The transaction MB52 not complete the requirement because I need show the time.... I need show the future deliveries due to i need analyse stock capacity in the logistic...

View Article

Cancel COFC error but posted HRS on orders

During last month end process order closing our FI team found - they were not able to close few orders because there we errors lying in COFC transaction. Now to clear these errors we have created...

View Article


Re: Batch Data

Hi Can we restrict this for some particular order type... Means if batches are created through some order type , user should not able to changed the DOM and SLED as its derive from batch derivation

View Article


Re: Distribution Key for Planned Order

Hi Ignacio, I think you can use BAdI MD_ADAPT_DISTRIBUTION to adjust the start andend dates/times for the distribution function.  This is the help document from SAP: ------------------- You can use...

View Article

Re: Distribution Key for Planned Order

Hi Radhakrishnan R, You can set up the Distribution Function to not have a yield during the set up time.For exmple, in your case, you can set upDuration 25% - Yield 0%, and thenDuration 100% - Yield...

View Article

Re: Mass update of Auth.Gr. for BOM

Hi, When I used SAP_BOM in Current Working Area received error message 'Entry SAP_BOM does not exist in T410 (check entry)'. Please advise.

View Article

Re: Mass update of Auth.Gr. for BOM

Hello  Could you please share the screen shot of the available entries in the Current Working Area. You can also go with the SAP_item in the Current working area.  Select Current Working Area as...

View Article


Re: LTP versus MRP scenario

Thank you Caetano!One last question, because i have never used this kind of BADIs: If i do this, as you suggest, is the simulation of safety stock going to "stay" only in the LTP scenario and will not...

View Article

Re: reservation issue

Hello Is the CUOBJ available on the planned order? Maybe the following note can be relevant: 2313748Configuration is not passed on to components BRCaetano

View Article


Re: LTP versus MRP scenario

It depends on the logic implemented on the BAdI. You can make the additional element relevant to LTP only or also to MRP. BRCaetano

View Article

Re: MCPS - LIS update the last changes on the production order as TECO - Time...

Guys Anymore has idea about the last doubts? Thanks Itamar

View Article


Re: LTP versus MRP scenario

Many thanks Caetano!I will check and come back.

View Article

Re: Batch Data

Hi, I believe you can achieve this via customization or use Badi. Not possible via standard. thanks

View Article

Re: General extra material's requirement when MRP

Hi Solomon,     Many thanks for your reply!  Yes, this problem should be in MM.  At last our MM consultant use free goods in info-record to solve it. BRMicrofish