Re: Xstep in Production Order

This is the correct answer for production order also

View Article


Image may be NSFW.
Clik here to view.

Re: To have planned order Basic start time as per factory start time

Hi Jay It works on my system when I'm creating a production order on CO01 or when I'm converting a planned order. Take a look on the attached screenshot to make sure that this is what you want. I think...

View Article


Re: To have planned order Basic start time as per factory start time

Hi Caetano, Cool..i think the Finite scheduling in the workcenter is the key..i will check that and come back on monday. great Thanks RegardsJay

View Article

Image may be NSFW.
Clik here to view.

Missing BOM components - MFBF

Hi Experts, While doing goods confirmation (MFBF) system is giving error as "missing BOM components" No material component available. Also please find the attached screen shot. Message No.: RM170...

View Article

Re: Missing BOM components - MFBF

Hi, Plea check stock of the BOM components also. Please make the stock available for the components and then try MFBF. RegardsAjay

View Article


Re: Missing BOM components - MFBF

Hi Ajay,  I have check the same but still not happening   regardsPK Sahu

View Article

Re: Missing BOM components - MFBF

Hi, In MFBF transaction you are trying to post the confirmation of finished good material.  As we know in MFBF, we do confirmation through backflushing wherein component materials required for...

View Article

Re: Missing BOM components - MFBF

Hello Sahu Please check below thread for your issue.  MFBF window Missing BOM Components error "no material components available" I hope this information helpful to you  Thanks & Regards Umesh Mali

View Article


Sales organisation and Distribution channel configuration

hello gurus, I am Azhar and I am new in PP so  I want to create full material master in IDES with its configurations but day to day I am facing problems.So please help me until its completed. thanks

View Article


Re: ROUTING CREATION

Thanks for your effort with some minor changes to the report I got the expected resultBest RegardsRamy Sully 

View Article

In which report can i get the Work center wise start and finish in hours.

Hi,I Need a small suggestion. Now i open CR03 Here i can able to see the work centers list.Under capacity tab and at capacity header i can see the Start time and Finish time.May i know at Which report...

View Article

Re: In which report can i get the Work center wise start and finish in hours.

Hello, Check CM01 under Detailed capacity list, here you have an option to choose fields as per your requirement. Available Capacity  table KAKO take the fields BEGZT(shift start), ENDZT(shift end) and...

View Article

Re: In which report can i get the Work center wise start and finish in hours.

Hello Try with transaction CR60. Select the option to change layout, click button "position" and add "start" and "finish" fields to the report. BRCaetano

View Article


Re: In which report can i get the Work center wise start and finish in hours.

HI, I open CR60  but i am not able to see the Start time and  Finish Time,but Start date and Finish date. i am able to see it.

View Article

Re: In which report can i get the Work center wise start and finish in hours.

When changing the layout you should select the option "position",

View Article


Image may be NSFW.
Clik here to view.

Re: Production Order cannot post 261

Hi Amit,  The final issue indicator is not be ticked.  Regards, Steve

View Article

Image may be NSFW.
Clik here to view.

Re: Production Order cannot post 261

Hi Rohit,  The production order status is REL  MSPT CNF  DLV  PRC  CSER GMPS RESA*. And 0522882816 is a reservation number.  Regards, Steve

View Article


Re: In which report can i get the Work center wise start and finish in hours.

Hi, Almost all i got the answer but.May i know Operating time and Capacity , Will it store in any table. I checked it forum some body told me that.it will be display at run time only. and i checked in...

View Article

Re: Production Order cannot post 261

Dear Viral,  The production order status is REL  MSPT CNF  DLV  PRC  CSER GMPS RESA*.Do you have any opinions? Thank you.Regards,Steve

View Article

Image may be NSFW.
Clik here to view.

Re: Production Order cannot post 261

Hello Brahmankar,  These three components are not backflush material. For snapshot of MB23, please kindly see it as below. What is meaning about 'Check GI been posted for the order before?'? Thank you....