Hi Jay
It works on my system when I'm creating a production order on CO01 or when I'm converting a planned order. Take a look on the attached screenshot to make sure that this is what you want.
I think that they key here is to use the scheduling "forwards in time" and to make sure that the first order operation is relevant to scheduling. Therefore, you should check the following settings for the first operation:
- The flag finite scheduling is set on the work center;
- The control key of the first operation is relevant to scheduling;
- The scheduling formula is defined on the work center;
- The standard values are correct on the routing.
Best regards
Caetano