Quantcast
Channel: SCN: Message List - SAP ERP Manufacturing - Production Planning (SAP PP)
Browsing all 2633 articles
Browse latest View live

Image may be NSFW.
Clik here to view.

WIP Batch in Subcontracting

Hello everybody, hope for your help.I have material A, for example. It is processed in operations 0010, 0020, 0030. Operation 0020 is external. There are three raw materials in BOM, let it be B,C and...

View Article


Change from Backward to Forward Scheduling in Planned Order ?

Dear Seniors, Our customer want to be able to change from backward to forward scheduling in Planned Order, in the same way they can do in the Production ORder.In Planned Order configuration I know is...

View Article


Re: Change from Backward to Forward Scheduling in Planned Order ?

Hi Alex, This is maintained in the Scheduling parameters for planned orders. Go to t-code OPU5, and you can change from backward to forward, or viceversa. Kind Regards,Mariano

View Article

Re: Change from Backward to Forward Scheduling in Planned Order ?

Hello I would like to suggest you to read carefully the following note, which explains the effect of the forward scheduling on the planned order: 1913017MRP: Forward scheduling and adjust basic dates...

View Article

Re: Change from Backward to Forward Scheduling in Planned Order ?

Hello Mariano, Thanks for your response.As mentioned in the initial discussion, we know about that option.If I update in the scheduling parameters for forward, then this will be the default.We want to...

View Article


Re: Change from Backward to Forward Scheduling in Planned Order ?

No, there is no such option.

View Article

Re: Change from Backward to Forward Scheduling in Planned Order ?

Hi Caetano, Thanks for your input.My understanding is that the basic start date defines the requirement date for components.Our scenario is:Backward scheduling for all orders set by default.In a...

View Article

Re: Change from Backward to Forward Scheduling in Planned Order ?

Hello As I mentioned earlier, there is no such option.  BRCaetano

View Article


Re: Deficit of blocked stock xx kg in ud reversal

Dear Ciao, Thanks for replay. Please tell me In OMJJ i have updated in 349 mvt in allow transaction area i have maintained in qa11 transaction. 321 also same things I have updated. Please tell any...

View Article


Image may be NSFW.
Clik here to view.

Routing operations getting deleted

Hi Team,we are facing a strange issue and the issue is as follows, we are bridging the BOM through the matrix to SAP.After this we are creating the Routing through CA01 and assigning the operation to...

View Article

Re: MRP type X0 in HANA

Hello On the customizing transaction OMDQ, you can create your own MRP type.Choose procedure 'X - Without MRP, with BOM explosion' and it will be similar to X0.BRCaetano

View Article

No order status if capacity is not checked in Production Order ?

Dear Seniors, In the production order, there is the option of capacity check.If the capacity is not available, we get the status MSCP. If the capacity is available or if the capacity has not been...

View Article

Re: No order status if capacity is not checked in Production Order ?

Hi, how about this status CPCKCapacity checked Did you check this? Is this status available? But I guess successful stuff will not be tracked. Best regards Patrick

View Article


Re: No order status if capacity is not checked in Production Order ?

Hi Alex, You can use report COOIS (COHV) and filter by system status:- CPCK (Capacity ckeched)- CANC (Cap.availab.not checked)- MSCP (Cap.shortage). Kind Regards, Mariano

View Article

Image may be NSFW.
Clik here to view.

Re: No order status if capacity is not checked in Production Order ?

Hi Mariano, Thanks for your input, it is exactly what I am looking for.In my production order, those statuses do not appear.Is there a customizing which can activate them ? Thank you,Alex

View Article


Re: No order status if capacity is not checked in Production Order ?

Hi Patrick, Thanks for your input. The status does not appear in my Production Order.I am working in a standard SAP IDES system, with order type PP01. Please let me know if you know about a customizing...

View Article

Re: Planning levels in Planning Hierarchy for Flexible planning

Thanks Rupesh,This is resolved now.Now I have another query about populating the info structure with the old data.ans configuring the planning hierarchy which i will ask in a separate thread.

View Article


Image may be NSFW.
Clik here to view.

Configure Planning hierarchy in Flexible planning

Hi, I am implementing flexible planning where i need to configure planning hierarchy. I have 5 characteristics in my planning hierarchy as shown below: 1) Sales Org2) Sales District3) Sales Office4)...

View Article

Material Consumed

Dear Members In my organization fabric is manufactured. I want to see how mauch material is consumed in a particular production order. From which tcode i can get my result

View Article

Re: Material Consumed

Hello,1. You can Check In CO02/COR2--GO TO--Documented Goods movement.2. In COOIS/COOISPI ,Select List = Documented goods movement,Pass the order and execute.3. You can get details in AUFM table also....

View Article
Browsing all 2633 articles
Browse latest View live


<script src="https://jsc.adskeeper.com/r/s/rssing.com.1596347.js" async> </script>