Re: MPS Planning Table updated but not MC94
Hi Brahmankar,Thanks lot for your valuable guidance and timely suggestions ThanksSakthi
View ArticleField old quantity is not being updated in ME38
Hi experts, We are using scheduling agreements and the delivery schedule lines are being updated in t-code ME38. After the delivery schedule has been sent to the vendor, the field old quantity is not...
View ArticleRe: RMCA9156 -Info structure field greyed out
Hello, The maintenance of variants for mass processing in SOP or in flexible planning is only allowed using Transactions MC8D (Create) and MC8E (Change).Use these transactions if you want to maintain...
View ArticleRe: Forecasting with MRP not correctly planning inventory
Hello, MRP type VV does not consider any sales order requirements.For a material planned using forecast-based planning, MRP only considers the forecast requirements. Other requirements are displayed,...
View ArticleMF50 with VMI solution
wish to improve the MF50 transaction in order to see actual situation as per Client requirement. Is it possible to include in MF50 or in z-report 1.Total Requirements = shipment to customer...
View ArticleCOGI questions
HI All I have an issues with the COGI. I am not an expert in SAP so I trying to understand COGI.The issues are below1.The production order is being TO and release to be produce.Some of the material...
View ArticleRe: COGI questions
Hi After you received the stock, Go to COGI ,select the line item againt production order ,double click,it takes to new the new screen.modify the quanity and save your cogi error will be cleared...
View ArticleRe: Planned order delete pop up
the status is generetd from the plantx-materials status which will be maintained in MRP1
View ArticleRe: COGI questions
Hi, 1) the stock is available. But is it available for the deposit that is in the order? Another thing, it can be that you have reservations of other orders 2)he/she has several cases:a) I have stock,...
View ArticleProcess Instruction Category selection in Process Order
Hi PI gurus, Can you please explain how the Process Instruction Category is selected for a phase of a process order from multiple PICs defined in the CRD? Thanks and regards,
View ArticleRe: Process Instruction Category selection in Process Order
Hi, Process instruction can come from the master recipes or IMG (or both) master recips: C202 > operations > mark phase > GO to > process management > process instructions IMG: Dimas...
View ArticleRe: Auto conversion of subcontract PR into PO
Hi Sankar, Could you please confirm what solution you went with? Thank you
View ArticleRe: To copy the component assignment
Dear,I opened a ticket with the Support SAP about this case, and not is possible to execute the copy component assignment one material for other. With the CEWB (tcode), only is possible: 1) First to...
View ArticleRe: Items sequence in overview tree for MD04
Hello Laura, This looks like transaction MD4C to me. May be you could define a custom logic via BADI MD_DISPLAY_ELEMENT. Please check this with your ABAP consultant. Best Regards,Ameya B.
View ArticleProduction scheduling profile-Order Type
Hi Friends, We want to Process/Production orders in a single plant. So created Order Types/Production scheduling profile separately and configured accordingly. Created material--> work scheduling...
View ArticleRe: Production scheduling profile-Order Type
Does that mean you don't want to create process order for other materials ? If this is so, Don't extent work scheduling view for other materials, system will not allowed to create process order for...
View ArticleRe: Production scheduling profile-Order Type
Hi I don't want to create production order for the material which has production scheduling profile of Process order. Regards,Srihari
View ArticleRe: Production scheduling profile-Order Type
Hi srihari, according to me production scheduling profile is used to specify that the which process are to be carried out in parallel in production or process order, Order release at the time the order...
View ArticleRe: Raw material quantity varies
When Raw material quantity is changing based on customer order ,it should be ETO and we need to create Fininshed product BOM and routing every new order. Maintaining same BOM and routing will...
View ArticleRe: Raw material quantity varies
We have 12 finished product types(thickness-width combination) and for each category we know our raw material BOM quantity and it is fixed.Is it possible to create 12 FERT and assign respective BOM to...
View Article