Re: Production order co-product

Hi Renato A co-product is usually produced by an order from another material. If you are creating an order specifically for this material, it is no longer a co-product. Please take a look on the...

View Article


Re: Production order co-product

Caetano, what they are consuming a material to generate a co-product, and it is generating a search on CS_WHERE_USED_MAT function as the co-product is generated in more than 1,000 products, it comes...

View Article


Want to change valid to date in BOM component uning change number

Hi, I have a BOM with 3 components 10,20,30 with valid from date as 01/01/2015 to 31/12/9999 now i want to change the valid to date of the 10 line item, is it possible? Now i want to change the valid...

View Article

Re: MFBF - Shift and Personnel number

I get the POP-UP screen and I enter the "Personnal #". However the system goes and checks if a "Personnal number" record exists in HR-record. !Can we have the number populated into AFRU - PERNR without...

View Article

Re: MFBF - Field for Employee ID

I replied with my question in MFBF-Shift and personnel number thread created by me.

View Article


MF41- There are inconsistencies in the postprocessing records RM857

We are getting an "Error" when we try to reverse a material document through MF41 (REM). ERROR- There are inconsistencies in the postprocessing records (RM857)

View Article

Re: MF41- There are inconsistencies in the postprocessing records RM857

Hello Please check the section Inconsistent “Nproc” dependent requirement from the WIKI Inconsistencies for planning elements and display problems on transaction MD04 - ERP Manufacturing (PP) - SCN...

View Article

Re: Want to change valid to date in BOM component uning change number

Hello I suggest you to create a new change number and use it to delete those components. BRCatano

View Article


Re: Old SubReq's Shown in MD04 & considered for Planning as well (No Preq found)

This also did not help

View Article


How to delete records in COFC

Hi I am getting error "unprocessed future change records for order prevent delflag/completion' while process order close. I could see that entries in COFC transaction.When I double click on process...

View Article

Re: How to delete records in COFC

Hello On the standard system there is no option to delete COFC records, as it can lead to costing inconsistencies. However, under exceptional circumstances, for example, when the records are very old...

View Article

How to split Planned order created in month for different requirement plan...

Hi Experts, I need assistance in configartion the the scenario where user creates 2 demand say for qty 10 and 10 each for month March under 2 different requirement plan for one material using...

View Article

Image may be NSFW.
Clik here to view.

Re: At Order release

Hi Sree, If you got your answer please close the discussion.  How to close a discussion and why Thanks, Vishal

View Article


Re: Old SubReq's Shown in MD04 & considered for Planning as well (No Preq found)

Hi Rahul, Please check, Inconsistencies for planning elements and display problems on transaction MD04 - ERP Operations - SCN Wiki What happens when you try to look for pegged requirement for these...

View Article

Image may be NSFW.
Clik here to view.

Re: Production is confirmation in Pieces and customer required weight as...

Hi, You can use serial numbers and use classification system to record the attributes like color and length against the serial number equipment master record. Try searching more on serial numbers . You...

View Article


Image may be NSFW.
Clik here to view.

Re: How to split Planned order created in month for different requirement...

Hi Milo, Please check below link, Hope you will get ur answer in this.  MRP: One order per requirement | SCN Thanks,Vishal

View Article

Plan cost in production order

Hi Recently I have noticed the following- I have created production order and selected Plan Cost at the time of saving production order. While checking the plan cost system have calculated plan cost of...

View Article


Re: How to delete records in COFC

Check instructions of SAP note 1858647 about the issue COFC 1858647 - PP: Unprocessed future changes recs for order xxx prevent del.flag/completion

View Article

Re: Auto batch determination for sales order stock

This is possible in standard without any enhancement. I did it. Thanks all

View Article

Optimum Lot size for production

Hi Guys, I have one requirement similar to minimum lot size, but having the small difference. If I put Min lot size as 60 and requirement is 55 system creates order for 60. The requirement is not to...