how to change order finished date for bulk planned orders
Dear sirs,i have to change order finish date for all planned orders in order to convert them into production orders.can you explain how to do that.
View ArticleRe: Terminate Plan order Conversion , if no BOM is selected
Hello,Earlier,I have deleted the component from the header material and was doing activity but in that case system shouldn't take a wrong material,Don't know why this strange behavior??I created a new...
View ArticleRe: how to change order finished date for bulk planned orders
Hello, I dont see a mass update transaction for planned orders, below are mass processing functions defined for planned orders, Mass-Processing Functions for Planned Orders - Production Orders (PP-SFC)...
View ArticleRe: Purchase Requisition not generated by Background MRP job.
Hello, What is the planning strategy for material? Mixed MRP Indicator is required for this strategy? Regards, Shekhar
View ArticleCleanup consignment stock batches
Hello Folks , I want to cleanup consignment stock batches having zero stocks from table MSKU Is there any program available for it. like we have for tables MSKA/MCHB/MSPR ( SAP note 62272). ThanksHaridas
View ArticleRe: Dump ERROR-Collective Order
Hi Gyan, Thanks for reply, but the forum not allow me to enter my email in the message (the reply was rejected after being reivewed).Is the correction program a SAP Note or any other standard program...
View ArticleRe: Wrong Issued Value Quantity In MCRE Report
Dear Rupesh, Thanks for your valuable reply, I will go through the given note If any problem/ query I will revert Closing the same Thanks & Regards,Madhukar Poul
View ArticleRe: COGI error
Hello, Cancellations of the goods movements are basically carried out in the update program (update task), that is, this does not depend on the settings in the Customizing of the OPK4 confirmation...
View ArticleCapacity Calculation Formula
Dear Experts,Here I am having a situation I am using standard Formula SAP006 and this formula says (Machine * Operation quantity / Base quantity) and currently I have taken No of Individual capacity...
View ArticleRe: Planned Orders and Holiday Calendar
Hello, Planned Order forward scheduling in MRP It is not possible in standard SAP.MRP considers the requirement date as basic finish date and calculates the basis start date using backward...
View ArticleRe: Dump ERROR-Collective Order
Hello The Rules of Engagement provides the following information: If you want someone to trust you enough to buy what you offer, share your expertise and they will seek you out. If you want people to...
View ArticleStrategy 63 and Forecast Consumption
Newby Question here: We have the following scenario: Plant 417 ships product for plant 217. Plant 217 has forecast against it. Plant 217 and plant 417 are both purchased items. Plant 417 has...
View ArticleHU items' material posting is inconsistent
Hello Guys When I try to reverse the outbound delivery with VL09, I get this error , I have one HU in my outbound delivery. Would you please help to find out the root cause ? Thanks a lot.
View ArticleRe: Good receipt error for prodution order(MB31)
Hello, Please check auto good receipt is active for order through control key or scheduling profile.Also check any error in COGI. Best Regards,R.Brahmankar
View ArticleRe: Archived Bom
Hi Steve Deletion is not archiving. If you followed the standard archiving process, as described on the link below, then you can access the BOM. The process to access the archived BOM is described also...
View ArticleRe: Planned Orders and Holiday Calendar
Hello If the issue is solved, please close this thread. Best regardsCaetano Almeida
View ArticleRe: Cumulative ATP Quantity in CO09 ?
Hello, An availability check is carried out by function module AVAILABILITY_CHECK_CONTROLLER with CALL FUNCTION AVAILABILITY_CHECK Best Regards,R.Brahmankar
View ArticleProcess order TECO and CNF
Hi Experts, I have a situation where i need to restrict TECO of process order if CONFIRMATION is not done. How do i achieve this? please advice Thanks and Regards,Aziz
View ArticleRe: ROH Production Order
Hello, What I can understand from four post is you have create a new order type for ROH materials. And when you do GR for these orders the 101 document is posted but the stock is not updated....
View ArticleRe: Good receipt error for prodution order(MB31)
Dear Expert, Very gIad to see your reply. I checked the control key and scheduling profile and found auto good receipt is not active, please refer to below pictures. Looking forward to your feedback.
View Article