Re: Planned Orders and Holiday Calendar

$
0
0

Hello,

 

Planned Order forward scheduling in MRP It is not possible in standard SAP.

MRP considers the requirement date as basic finish date and calculates the basis start date using backward scheduling

During the MRP run, a planned order will be always firstly scheduled backwards according to the in-house production time defined on the material master. In this process, system considers the requirement date and schedules the planned order backwards to calculate the basic start date.

 

Please see the OSS note 603487 - Matl reqmts planning: No switching to forward scheduling

Forward scheduling on MRP

BAdI available to influence the scheduling of a planned order is MD_PLDORD_SCHEDULING.

 

Regards,

R.Brahmankar