SubReq Consuming/Reducing Forecast (VSF)

Hi, I would like to know how to attribute MRP settings so the subreq consumes/reduces the material's forecast (VSF). This issue only applies for a finished good that contains other finished goods....

View Article


Re: SubReq Consuming/Reducing Forecast (VSF)

Hello Check the following points: 1 - Field Mixed MRP is set to 1 on the material master.2 - On transaction MD62, set the field 'Consumpt.ind.' to '3 - Consume customer reqmts, reserv., dependent...

View Article


WIP Batch - Linking Final Goods receipt batch with last WIP Batch

Hello Gurus, I am not able to link final goods receipt batch with last WIP batch after final operation confirmation.  I am creating link between GR batch and WIP batch using button WIPB --> GR. I am...

View Article

Re: No Requirements For Components (ROH)

Hello Did you check if the parent material BOM was correctly exploded? If this raw material component there? You can check the value of field "MRP dep.requirements", which can be used to make dependent...

View Article

Re: Stock not posted after GR of production order

Hello, Search on SCN or else go through SAP Help once. You will understand the concept behind generating settlement rules.Please refer my reply from this discussion,Production Order Issueand SAP FAQ...

View Article


Re: VSF reqs Splitting

Hello On transaction OMPH you can define a period for automatic split of PIRs, but it is only relevant when PIRs are transferred (from APO or SOP, for example). If this is not the case, you can use...

View Article

SAP PP in hot rolling mill

Hello membersPlease clarify a basic doubt. A hot rolling mill producing steel coils out of  steel slabs is said to be a process industry but I have seen SAP PP discrete manufacturing being implemented...

View Article

Re: OP21 Allowed for calculation indicator

Hello, Unfortunately I executed the report RCR05GEN and tried with a new process order again, but the costs are still calculated. Thanks for your reply anyway. Kind regards,Ion

View Article


long term forecast MD30 query

Hi Gurus, could you please suggest me reorder point planning will allow MRP to procure materials based on the long term forecast MD30 to reducing the available stock below the reorder point. RegardsSada

View Article


Image may be NSFW.
Clik here to view.

Re: OP21 Allowed for calculation indicator

Hi Jon,I cannot find where that field V_TC25-VKALK, neither its data element or main field in table TC25, is used in SAP programs. Therefore, I'm not sure if it has the effect you need.In OSS note...

View Article

Changes in ECN

Hi Experts, i am using ECN for recipe management. Once the ECN is released, further changes to recipe is not allowed by system with the same ECN.But the ECN itself can undergo change in description,...

View Article

Re: SAP PP in hot rolling mill

Hello Yes, it is possible, but it it is always preferable to go for the industry solution DIMP, as you have special functionalities, such as the order combination. Please be more specific regarding...

View Article

Hello sir Is there any way or T-code to copy ops from production order to...

Hello sirIs there any way or T-code to copy ops from production order to excel with all long text.

View Article


Re: problem in the classification of the products

Hi      It may be helpfull For You Transfer of characterstic values from class 300... | SCN

View Article

Re: No Requirements For Components (ROH)

Hello, Planned orders will only generate dependent requirements which would be converted into order reservations/dependent reservation when planned order is converted to a production order. Against the...

View Article


Re: problem in the classification of the products

we just have a problem when we changed  the data of class type Z01 in master data of material .

View Article

Re: problem in the classification of the products

I'm sure it's not relevant to order . when I create the material and define the class type Z01 , before create the production order or BOM , I changed the class type Z01 ,but when we want to confirm...

View Article


Re: problem in the classification of the products

Hello Ali, Please debug and check with help of your ABAP team why it is still picking up the same old value of 80 when you have changed it to 60. Also did you try creating a new production order and...

View Article

Re: problem in the classification of the products

The question is if your batch that is used in your production order  already exists when you change your material master classification.If the batch already exists then the value of the characteristic...

View Article

Image may be NSFW.
Clik here to view.

Re: problem in the classification of the products

new batches also have problem unfortunately. 