Dear Expert,

 

 

We make a production through sub contracting . we send component material to jobber for FERT production , some of the time some stock lying with jobber , that is reflected in MD04 list under each component material below the list .  We want to know during MRP execution , if any stock having  with jobber in our book ,  PR will  be generated after considering both the stock ( own stock + stock lying at jobber) on the  basis of dependent requirement .

 

Please let me know the procedure.

 