Hello
You could only run RCCP for a material if there is demand created for it on SOP and, as far as I know, there is no BOM explosion on SOP.
Since the actual bottleneck for the finished product is your semi-finished product and not the work center, you can create a Rough-Cut Planning Profile for the finished products where the resource type is a material instead of a work center.
BR
Caetano