Hi Mariano,
Thanks for your time to given me the reply.
We are not changing any dates, when i enter the t-code, it automatically shows todays date, we put the part no. and execute it, then also it missing some parts in the structure BOM. why?
Also we see the cost structure through MM03 - enter an material no.---go to costing-2---under the Standard Cost Estimate---Click on Current and it'll displays the Material Cost Estimate with Quantity Stucture,so here only when click the arrow mark down then BOM structure shows with price, here only i noticed that it missed the some material no's which is already updated in the BOM (CS02).
So can you suggest me why its missing or any other way to get a Cost structure with all BOM parts involved?
Regards,
Santhosh.