Hi Gurus,
we have a client requirement; where there is no Sales Order will be there to consume the PIR quantity. But client wants to reduce the quantity through a Z-movement type.
But in MD04 screen after the PIR quantity is consumed and again they create some more PIR's for next upcoming month's then the system is considering the old PIR and generating planning.
I would like to know is there any way to stop this so that once the PIR quantity is consumed by the respective Z-movement type system should delete the PIR or not consider in planning (by configuration and z-enhancement)
Any flash lights will be great full...
Thanks & Regards,
Mac