Hi,
Based on further tests, the Start Date is not the first parameter considered for ATP quantity commitment.
If the order with start date 15 September would result in a lower confirmation factor, then the one with start date on 20 Sept, the later order with start date on 20 Sept will be picked. It will result in a higher confirmation factor
I guess that after the confirmation factor, the next parameter is going to be the order start date ...