Re: ATP Check sequence change in MDVP ?

$
0
0

Hi,

 

Based on further tests, the Start Date is not the first parameter considered for ATP quantity commitment.

If the order with start date 15 September would result in a lower confirmation factor, then the one with start date on 20 Sept, the later order with start date on 20 Sept will be picked. It will result in a higher confirmation factor

 

I guess that after the confirmation factor, the next parameter is going to be the order start date ...