Re: Manual printing for a Production Order Type ?

Hi Alex As our fried Velmurugan pointed, the customizing to define if the order will be printed on release is available at production scheduling profile and this profile is assigned to the material,...

View Article


Change Dates in Release Process Order

Hi AllNeed your suggestion in below scenario.I want to change the dates in released process order.Will explain you reason behind this.1.Process order is created.It has subcontracting process defined in...

View Article


Reduction of planned independent requirements goods receipt for a production...

Hi Gurus, I have a fert that consumes a halb. I would like to put the RIP only HALB, and when making a goods receipt for a production order to consume the RIP of HALB. What strategy should I use? I...

View Article

Image may be NSFW.
Clik here to view.

Re: Change Dates in Release Process Order

Hello   You can still change the scheduling date by clicking the edit button below for released orders: Regards,Velmurugan S

View Article

Re: Reduction of planned independent requirements goods receipt for a...

Hello You can use the Gross Requirements Planning (11)  for your requirement where reduction of planned independent requirements takes place during goods receipt for a production order (Dscrete), for a...

View Article


Re: Reduction of planned independent requirements goods receipt for a...

Hello Leandro The only planning strategy that allows you to reduce the PIR during the production order goods receipt is strategy 11, however, you must consider that this strategy does not check the...

View Article

Re: ABAP dump on COR1 while make change in include ZXCO1U01

Thank you Sir,I have shifted validations from PPCO0001 to PPCO0007 and now it is working ok with out any ABAP dump. Regards,Archana

View Article

Re: Change Dates in Release Process Order

Hello I don't think that the scheduling will consider any change on the subcontracting order delivery dates. You must adjust the dates manually.  BRCaetano

View Article


Re: Issue in PR from Sale order in mrp run

MRP type : m0. Lot size -  EX No planning alendar.  Thank you . Siva.

View Article


Re: Issue in PR from Sale order in mrp run

Tot. repl. lead time 0   days.

View Article

Image may be NSFW.
Clik here to view.

Re: How to set a printer to a workcenter when shopfloorpaper has to be printed?

Hi, In OPK8 transaction maintain the settings for the order type, plant, List combination. i.e. Select WCPr (Work center printer). Also, assign the printer in the work center (Default values TAB Page)....

View Article

Re: Issue in PR from Sale order in mrp run

Hello                 It seems to be that material uses Planning time fence( in MRP1) .Do you use  the Planning time fence periods ? Regards,Velmurugan S

View Article

Re: Issue in PR from Sale order in mrp run

Hello,  Check the planned delivery time. Maybe the replenishment order can not be created earlier because of the planned delivery time.If this is not the solution, it would help if you can share with...

View Article


Re: Production version without rounting

Hello On your scenario you only need to create a production version if there are several alternatives and you want to select one specific alternative. If this is not the case, you should go for...

View Article

Image may be NSFW.
Clik here to view.

Re: Issue in PR from Sale order in mrp run

Hello Probably the flag "start in the past" was not checked on the customizing transaction OPPQ. In this case, system cannot create a replenishment proposal with the start in the past, therefore, it...

View Article


Re: Backflush at Line level for planned orders at Machine level

Hi R,That I had checked already and did not work because the Planned Orders were created at Machine Level and Consumption was done at Line level, so the Planned Orders remained unconsumed. ThanksDeepankar

View Article

Re: Restrict planned order creation

HI Velmurugan/ Venkatesh,thanks you for suggestion.We can not implement this option as we are using MD11 in custom transaction. Another thing is client  just want to restrict planned order creation...

View Article


Re: Restrict planned order creation

Hello,  In this case,  since you are using a custom transaction you have multiple different options to do it in your program. Talk to your programmer and modify the program in order to restrict it....

View Article

Re: Production Order Cancellation

Hi Rupesh, I have a small question, to set the line item as a rejection I have to do all the goods movements reversals with respect to Production Order. Then, I have to activate the respective...

View Article

Re: Production Order Cancellation

Hello, What is the error message are you getting? Best Regards,R.Brahmankar

View Article