Committed quantities appearing in CO09
Hi All, Committed quantities still appearing in CO09 for old order reservations in the past date in the field committed qty/confirmed in CO09, however, these old order reservations (appearing in CO09)...
View ArticleRelationship between PBED/PBIM and PLAF
Dear All, 1. I have created one Planned Independent Requirements PIR document through MD61, I am able to see the PIR records created in PBED and PBIM tables - PIR document no 121 2. I ran MRP...
View ArticleRe: Relationship between PBED/PBIM and PLAF
Hello There is no direct relationship between the planned order and the parent requirement (reservation, independent requirement, etc...). See my answer on thread the relationship between production...
View ArticleRe: Alternative BOM creation with change numbers.
Hi, In screen 1 & 2 , i noticed that valid from date as 06.12.2104.Is it RIGHT ???? Please check and get back. I hope this is the reason, why the system can't find a valid BOM on 13.06.2016. Thanks...
View Articledemand based MRP
Hi all, I have a requirement. I need an MRP type that it will trigger PR's only based on reservations (if any exists) with the quantity of the reservation. So lets say, I have a material with zero...
View ArticleRe: how to do sub contract process in operation wise
Hi Albun, I have some pdf presentation from SAP about WIP batch which I can share it with you.Please share your e-mail ID privately. Thanks,Ramesh
View ArticleIncorrect conversion while reversing the production confirmation.
In our scenario while confirming the production order using CO11 the consumption batch (261) will be in LB and produced batch (101) will be in KG. After putting up the KG quantity for 101 item the...
View ArticleRe: demand based MRP
Hello MRP type PD with lot sizing EX can cover reservations as you expect to do. BRCaetano
View ArticleRe: non pegged demand
Hi Rodney If the material master is correct, the sales order was probably created before the correct settings. Note 1649669 , which is mentioned on the document, suggests you 2 different procedures...
View ArticleRe: Operation scheduled time in order less than routing simulated time
Hello I suggest you to read carefully the following note: 150007 - Consulting: Scheduling of production orders This note provides the information below:* Have you defined not only units of measurement...
View ArticleBasic Start Date and Scheduled Start Date on Production Orders
Hi,I have created Prd Order and identify the cause for why when the order start date 06/14/2016 and with forward scheduling total Qty 1 or 2, then schedule the Order and check the dates its become...
View ArticleRe: Is it possible for me to use the costing BOM (usage 6) for LTP scenarios?
Hello This kind issue should not be raised to SAP as this is a consulting issue, rather than a possible bug of program error on the standard system. Yes, it is possible to use a costing BOM for LTP....
View ArticleHelp with demand planning disaggregation
Hi experts, Please I would like to ask for your help with an issue. Let me give you a brief description of the situation. We are creating a planning version thru MC87 transaction.We upload a file...
View ArticleRe: Error in Backflush MFBF REM
The inconsistency usually caused due to changes in Pegged requirement for the component doesn't flown to the component level.Since you ran the ZINCON_REPROC report, normally you should not face the...
View ArticleASSERTION_FAILED due to COGI in CORUAFFW program
Hi Experts, I am getting short dump as ASSERTION_FAILED during cogi posting in CORUAFFW. Please find the attached screenshots for the information.Please help me on this issue,I have checked some oss...
View ArticleRe: CO14 data missing / Table AFKO no updated
Hi again. Our program never sends to bapi the RUECK number, only the order number... Do you know any solution to adjust the field AFKO-IGMNG for one record with the indicated in AFRU? Thanks a lot...
View ArticleRe: Help with demand planning disaggregation
Hello Venkatesh, I tried to use the steps you describe for MC87, but when I try to split on to days I get the message: MA494 "Split the periods in ascending order"
View ArticleQuery for multiple MB56
Good day all, I need to write a query which would show the same as MB56, for multiple material numbers / batches.I was wondering which tables I need to use. Thanks to allThierry
View ArticleRe: Query for multiple MB56
hi Thierry, in my opinion query would be bit difficult rather you make a program hope this helps, https://scn.sap.com/thread/844315 regards,Solomon
View ArticleRe: Error in Backflush MFBF REM
Hello As already mentioned here, the report should be executed for the components, not for the finished product. BRCaetano
View Article