Re: Which transaction I have to use to see items for a production order?

Hello Rebeca, goto component view in Co03, here you should see materials flagged as Co-product for example BR Sabine

View Article


Re: GR MIGO not possible for WIP Batch

Dear       Please share the screen shot of MMBE . Try GR with Movement type 103.

View Article


Re: Missing Part Problem

Thank You sir

View Article

Re: Check Material QTY

Hello, Please check the Scope of check OPJJ for yourAvailability check and Checking Rule combination Check without RLT is ticked or not  read the F1 help of that field.  Items for which the delivery...

View Article

Re: quantity withdrawn but still some components are showing in co27

hi , The final issue will be automatically ticked right ?

View Article


Re: quantity withdrawn but still some components are showing in co27

Dear          What i understand ,if whole quantity is issued then why components are not set  Final issue . If the components are set final issue then it will not display in co27. there is...

View Article

Re: Stop planned order creation - MRP

Hello I suggest you to create PIRs using use planning strategy with planning without final assembly. This strategy will generate VP planned orders, which are not convertible and they are used only to...

View Article

Re: Blocking the creation of a planned order from sales order

Hi,in SO customizing for the schedule line vov6 you can try to use one not passing requirements. BR

View Article


Re: Blocking the creation of a planned order from sales order

Hello I suggest you to use planning strategy 10. With this strategy, sales orders are not relevant to the creation of planned orders and MRP will only consider PIRs during planning. See the following...

View Article


Re: quantity withdrawn but still some components are showing in co27

thanks . Got the solution issue closed

View Article

Re: quantity withdrawn but still some components are showing in co27

closed

View Article

Re: special procurement key OMD9 setting

HelloDid you check if the planned order/requisition generated by MRP was for stock transfer? Can you please provide a screenshot? It is possible to make a stock transfer not relevant to MRP using a...

View Article

Re: Automatic Period Split

Hello Automatic split only happens when PIRs are transferred to demand management (for example, from APO or SOP). I believe that you can schedule a periodic job to run the program behind MD67, so that...

View Article


Re: MRP Run with Quota Arrangement

Hello Pratik, This we can maintain through Source list and Quota arrangement  1.Maintain the lot size (Consider Quota Tick mark)2.maintain the quota arrangement usage 4 in the MRP2 View 3.Create the...

View Article

Re: New layout Profile cy38/cy40

Hello, What is problem you have?Did you tried these steps?  Transactions CY38 & CY39 we can have our own display and sort fields in the left side (Tabular form) of the CM25 screen. Create Layout...

View Article


Re: MRP Run with Quota Arrangement

Hello Venkatesh, This all setting we already did and we run MRP, but the problem is our requirement is getting split between 2 supplying plant (warehouse & production plant) directly without...

View Article

BOM Alternative item group

Hi all, I am taking BOM alternative item group for components. Giving priority 1 & 2 for two components. For first component usage probability 70% and for second component usage probability is 30%...

View Article


Re: Collective printing of spool no

Almeida thanks for replying... On releasing the production, two spool request generated. One for production order and other for GR list. When i select both the spool and print, system is printing but...

View Article

Re: Error in goods movement when confirming excess Quantity than the order...

Hi Venkatesh, Thanks for the reply. I had already maintained the same in OPK4. But still  101 movement type is going to COGI. Regards,Hemanth.

View Article

Re: MRP Run with Quota Arrangement

Hi Pratik On the standard MRP, there is no logic to check the stock on the supplying plant before choosing a source of supply.  If you want to implement this logic, I suggest you to use BAdI to choose...