Hello Everyone
We are following the below process flow.
- Operations are confirmed for yield & rework quantities in the operations.
- Once the rework quantity is confirmed, Rework operations are added manually in the order with rework quantity to process the quantity.We have three numbers of operations for rework.
- While confirming the rework quantity, scrap are also confirmed, but the subsequent rework operations doesn't consider the scrap quantity & the default value is populated as the rework operation quantity.
I have few question here.
1. What is SAP standard here ? Rework operation doesn't consider scrap quantity, & each time populate the default value as quantity to be confirmed, do we scrap quantities in each of the rework operations to report that the scrap has generated from the rework operations.
2. In this, again after scrapping the quantities in rework operations, I will again have to scrap quantity in the main operation which has generated the rework to ensure the subsequent operation has the lesser quantity to be confirmed.
3. What is the best practice here to report scrap generated out of rework operations.
Regards
Akilahmed