Hi,
1) Planning horizon value is 365 in table T399D. Table T483M is empty, so Planning horizon is maintained on plant level. I cannot check whether the planning horizon has been assgined to the relevant MRP gorup as I'm missing some user rights until next week.
2) Lot size used is EX = Lot-for-lot order quantity