Venkatesh,
The LTP does the following by using CM38 - report.
1) Capacity requirements are calculated based on the process orders, planned orders and simulated plan orders by Work Centers.
2) The total of Work Center / Cost center and Activity types will be transferred to CO plan version as scheduled activities. CM38 will shows capacity requirements by material / week .
is that clear?
regards,
Dave