Re: Planned Order finish date takes more time for higher Quantity sale order

$
0
0

Hello Karan

 

It means that the lead time for such quantity is too long and, in order to avoid a planned order starting in the past, system uses today as the start date, scheduling the planned order forward.

 

I suggest you to check the in-house production time defined on tab work scheduling or the times defined on the routing, if  you are using detailed scheduling.

 

If it is OK for you to have a planned order starting in the past, then you can change the respective customizing on transaction OPPQ.


Regards

Caetano