Re: Explosion date as start date of the production order in backward scheduling

Hi Nitish,

 

Try changing BOM explosion indicator in MRP 4 view to 1 - Selection by explosion date and test again. Also check if there is a MRP group maintained in MRP1 view of finished material. If so, make changes in OPPR transaction as well for that MRP group.

 

Regards,

Rohit