Hi Gurus,
i'm facing an issue about scheduling and work center shift.
Factory calendar is set as 5 working days (mon-fri).
On a particular WC i set as standard shift the following (same working days):
When i create planned order scheduling (set as forward) is carried out correctly, the start day remains the one i set.
Before:
After:
If i change the shift as following to overwrite the factory calendar and make the weekend days as working
When the scheduling is performed in the PO the start production date move some day before the one i set:
Before scheduling
After scheduling
Of course if i don't set the '1' for calendar overwrite the scheduling is not affected by the saturday and sunday new available capacity. But i need it for setting particular weekend as working and make them relevant for scheduling.
The same behavior if i set in the WC the factory calendar as 7 working days and i don't set the '1' (in this case not required).
The problem is the sunday shift, because if i set only the capacity for the saturday the scheduling is carried out correctly.
Anyone know why the system anticipate the starting date???? And how avoid it?
Please advice.
Thanks.