Hi Experts,

 

I want to set substitution process and I need your help.

 

In fact, I'm interested on what SAP could do in standard regarding the following process.

 

- I have some forecasts and stock on material A till the end of 2016.

- The business want to substitute material A by material B (new part:  0 stock; 0 forecasts) by the end of august 2016.

 

The requirement:

 

1- How can I switch the forecasts of the material A to B from 01-Sep-2016 to 31-Des-2016?

2- How can I set up the MRP to consume material B forecasts using material A residual stock from 01-Sep-2016?



Thank in advance for your help