Re: Single planned order requirement of Semi-finished & that  SFG is part of BOM of multiple line items of sale order

$
0
0

Dear Rupesh,

I couldn't get the right answer yet. Probably i am not able to make u understand my exact requirement.

I understand that using collective requirements, it will club all requirements of a material of the same date and will generate one planned order for them.

And using individual requirement, it will generate planned order against EVERY LINE ITEM of sale order. Correct me if i am wrong.

 

But my client wants that if the SFG is common among finished materials BOM and that finished materials are line items of sale order then it should club requirements of SFG against that sale order and should generate planned order  & if an-other sale order exists for the same finished materials then it should generate second planned order against requirements of second sale order! BOTH requirements from sale order are on same date

 

IF i use collective requirements indicator for SFG, system ll generate single planned order against both sale orders ( Which i dont want)

IF i use individual requirement indicator for SFG, system will generate planned order against every line item of sale order ( I want to generate planned order against clubbed requirement of line items as line items finished materials have common SFG in BOM) / PER SALE ORDER

 

Hopefully it clears you dear