Hi Rupesh ,
One more thing need to noticed that we are using planning date as current date in the MRP variant .
We don’ have any material number in planning file (MD21) where NETCH date as “Current date “ in system
If we keep it blank then will it work , what is the use of this when we are using processing key as “NETCH” ?
What is the best practice , we should keep it blank or it should be current date ?
Thanks ,
Regards,
Aman