Dear Ruphes,
i would like to check some component only in production order ATP and not consider them during the preliminary check in planned order.
For example:
Plannned order
Component 1 02
Component 2 02
Stock
Component 1 100 %
Component 2 80 %
Header result 80 % for planned order.
Component 2 in the planned order is not important for ATP check and if i don't change that to KP (or don't exclude it from ATP check) the global result of header planned order is influente affected by it (not 100)
I would like to by-pass the component 2 in order to have check only in the first component so that thre header result il 100 % .
But in the future when the planned order will begin production order the component 2 should be check with the master data value (02).
Is there any setting o badi/exit for do it?
Thanks a lot Ruphes , i don't know if i have described correclty my problem
Daniele