Hi Paris,

 

As suggested by expert Rupesh you can use the STO process between two plants

 

by creating the Stock transfer purchase order from the receiving plant to supplying plant.

 

against that STO PO supplying plant will do the goods issue through 351 movement

 

then receiving plant can be able to do the 101 movement with reference to the same STO PO

 

Assumption:

 

Item category U has to maintain in the Stock transfer PO

 

Through MRP :

 

Create a Purchase info record in receiving plant by putting the Vendor code as a supplying plant

 

Assign the same vendor code in Source list by maintain the MRP Relevant

 

Run the MRP in receiving plant system will generate the PR convert to PO simultaneously system has generated the ORD DS proposal in the supplying plant

 

maintain the procurement type as E in the supplying plant and make the production then issue the component against the ORD DS (ST PO) through 351 movement

 

 

Regards,

 

Venkatesh.