Hello.
We have production version for material "A". In the BOM of "A" there are material "B", which has production version too.
So we need to plan this - create recuirement for material "A". Run MRP and get planned orders for "A" and "B".
So:
1. Create planned independent requirement in MD61 for "A". And put needed production version in Schedul.Lines view.
2. In MD04 I can see our independent requirement.
3. In MD02 I do MRP run.
4. In MD04 did not change anything. But in COOIS planned order was created for A. Why I can not see it MD04 too? And why planned order did not created for material "B"(dependent requirement was created)?
5 In MD02 I ran MRP. The situation repeats. And new planned order creates (can see only in COOIS). But old planned order does not delete. Why?
Parametres:
MRP views for "A" and "B":
VIEW1: MRP type - PD, lot size - EX
VIEW 2: Procurement type - X
VIEW3: Strategy group - 11, Mixed MRP - 2
VIEW4: BOM Selection metod - 2 (by production version).
MD02 RUN: NETCH, Create purchase Key - 1, SA Deliv. Sched.Lines - 3, Create MRP List - 1, Planning Mode - 3, Scheduling - 2.
When planned orders creates it has just indicator "Conversion indicator", and not have Firming planned order. So I think after next MRP run this planned order must delete.
Where I do wrong?
Some point. I noticed. If I do not set production version in MD61 - I can see planned order in MD04 after MRP Run.
And in MD21 there not indicators for my MRP area. I tried to put it in MD20. But after MRP run they desapeared.