Activity Price is not capturing in process order costing view.

$
0
0

Dear friends,

 

I have done all configuration and master data maintained for activity cost calculation in process order,in that only water price is not capturing in process order costing view.

 

Please find the screen shot and suggest me how to solve the issue.

 

Water = volume – L

 

 

 

 

 

 

 

 

1, COR1-(process order) – Costing View.

 

In the above screen shot the water price is capturing as “0”.

 

 

 

 

 

 

 

 

 

2, C202 IN RECIPE VIEW.

Here we have maintained everything properly.

 

 

 

 

3, Price updated in kp26 for the activity type 500247=1000 L.

4,Parameters for water 5000247 =1000L =40 RS

In SAP we have matained the dimention as Volume for water.

 

 

5,Water Volume =  L

 

 

 

 

 

 

 

 

 

 

 

6,Standard value key formula

 

7, Costing Formula for water.

 

Thanks&Regards,

Sabhapathy R