Hello Bramhankar,
The requirement is as follows,
I want to give day wise schedules for the next 30 days (i.e next month) which will be a firm order & monthly requirement for 2 subsequent months.
EX:-
The material has delivery lead time of 60 days, so the requirements for the month of june should be given before april 1, as the material consumes large space i dont want to stock it & want to receive it every day based on the requirement.
Now i dont know which machine i would manufacture on which day in the month of june right now but i have a forecast of the total number of machines for the month.
I run MRP now & give a monthly figure for june now & is it possible to change them to day wise schedules in the month of may?